Construction Update: Building #4, #6, Pool, Events Center

Latitude 44 has been a busy place the past few weeks. Keep reading to learn more about the construction going on at L44!
IMG_5037

Recently, we’ve broken ground and started construction for building #4. Building #4 will be an 8-unit townhouse, with six 3-bedroom units and two 2-bedroom ranch units on the ends of the building. We are expecting to have this building completed by October. There is only 1 3-bedroom unit available, but both of the 2-bedroom ranch units are still open.

IMG_5023

Construction on is moving along
nicely on building #6. The siding is going up and windows are being installed. Building #6
will be a 6-unit townhouse, with four 2-bedroom units and two 3-bedroom units. We are hoping to have this building completed by September. There are no units available for rent in building #6 at this time.

The pool has been poured and is in the final stages of completion. We expect to have it ready soon!

IMG_5028

Construction on the events center is moving along smoothly. The framing for this building recently went up. The events center should be completed in no time!

IMG_5030

Stay tuned for more updates on the L44 community!